Emergency Faecal Sludge Management – Lime Treatment
Description of the emergency context
Bentiu IDP camp located in Unity state, South Sudan hosts a population of 102,811 as of October population count. The camp has been in existence since 2014 as a Protection of civilian Site (PoC) established after the conflict displacement. In March 2021, the PoC transited to and IDP camp. In 2021, Unity state experienced severe flooding and in September 2021, the flood water reached Bentiu with water levels picking significantly around mid-November 2021 to an average water level of 1.2m. The rising water levels forced residents to flee their homes to nearby higher grounds, destroyed livelihoods and infrastructure, disrupted service delivery, and cut-off the supply chain; leaving displaced population overcrowded in temporary sites and to protect human lives form the flood treats dykes were constructed around Bentiu.
Description of the treatment process
IOM with support from MSF established an emergency faecal sludge management plant (FSM) within the IDP camp in order to manage liquid waste in the camp to avert any public health hazard since the access to the oxidation ponds was cut off by the floods. The operation of the emergency FSM plant started from the 13th October 2022 until 22 January 2023.
IOM used lime to treat and ensure pathogen reduction of the influent by raising of the pH levels to high alkaline conditions.
Assessment & design (feasibility)
Construction
Operation and maintenance
At its establishment/ inception IOM has been treating on average a minimum 40 cubic of liquid waste per day at the plant, however this was far below the faecal sludge production levels in the IDP camps, and more latrines were observed to be filling up and in need of desludging. The minimum of 40m3 per day was done considering lime treatment requirement. This then called for increase in the treatment capacity to a daily average of 120m3 to reduce the public and environmental health risk in the IDP camp. Additional treatment tanks 1*T70m3 and 1*T45 m3 tanks installed to accommodate the treatment requirements including installation of additional drying sludge drying beds.
Area of the Plant – Bentiu IDP camp FSM lime treatment site has a surface area of 2019 square meters including the dry beds.
Summary of the Emergency FSM operational cost
The greater part of the operational cost is calcium hydroxide (hydrated lime), it is shipped from the capital city Juba through airlifting. The Purchase price for 1*25kg bag of lime is at $13.00 and shipping cost through airlifting is at $54.17 bringing to a total of $67.17 per 25kg bag (purchase and transport).
Additional operational cost include equipment, site maintenance, fencing daily casuals incentives, pumps & piping, fuel, PPE as summarized in table 1.
Lessons learned
• Lime powder is corrosive and can affect the skin and respiratory system, and this calls for training of the staff to ensure safety protocols and proper PPE to the operators.
• Weather affects the drying period of the sludge from the dry beds, longer time to dry during the rainy days and 5-7 days during dry periods of temperature above 30oC.
•Adequate mixing of sludge is an important aspect to ensure effective lime treatment and to achieve this, lime to be mixed first with raw water, form a slurry after which is mixed with the sludge.
Strengths
• FSM plant easy to set up and start treatment operations for emergency settings to avert public health challenges.
Weaknesses
Even though the Lime treatment plant is easy to set up, in the case of Bentiu, there is need for prepositioning of lime. In Bentiu, the cost of lime procurement and transportation is high upto $67.17/ bag.
Road access is a challenge with only a short window per year to use the road, living air transport as the main option. In Bentiu, the FSM plant can only be effective for a shorter period (emergency) considering the daily treatment needs and high operational cost.
Add new comment